An Order 1 Soil survey must be
completed by a person who is certified as a professional soil
scientist by the Association of Ohio Pedologists or ARCPACS and
is registered with the Fairfield Department of Health. The
survey must illustrate the location of the required 2.0 acres of
usable acreage. The following items must accompany the
Order 1 Soil survey:
-
A statement that the proposed sewage treatment system(s)
on the proposed lot(s) will not be within a floodway,
100-year flood plain, or wetland.
-
A statement that the proposed sewage treatment system(s)
on the proposed lot(s) will not be within the isolation to a
public water system.
-
A statement that the proposed sewage treatment system(s)
on the proposed lot(s) will not be within an area where site
and soil conditions would prohibit sewage treatment systems
and will not require an NPDES permit from Ohio EPA.
-
A scaled drawing showing:
-
The existing and proposed lot lines with dimensions.
-
Designation/location of each soil boring/excavation
location.
-
Zoning setbacks (when applicable).
-
All hardscapes and disturbances (existing homes,
driveways, filled areas, etc.) on the proposed lot(s).
-
Existing or proposed easements, streams, and other
items outlined in FDH Regulation 18-07(4) requiring
isolation distances from sewage treatment systems.
-
Natural features on the lot affecting the
installation of sewage treatment systems (vegetation,
streams, drainage patterns, etc.)
-
Private water systems within 50 feet of the proposed
lot(s).
-
Public water systems within 300 feet of the proposed
lot(s).
-
Any designated FEMA floodway, 100-year flood plain,
or jurisdictional wetland subject to a US Army Corps of
Engineer's 404 permit or Ohio EPA 401 vertification.
-
Minimum 2.0 acres of usable area for each proposed
lot.
-
Topographic detail with contour lines in two-foot
intervals in the 2.0 acres of usable area for each
proposed lot.
-
Scale and North arrow.
-
Include an ODH Site and Soil Evaluation Form for the
most restrictive site of each soil identified in the 2.0
acres of usable area during the Order 1 Soil Survey.
An Order 1 soil survey must be completed for each proposed
lot including the remainder, unless the remainder is currently
used for and will remained used only for agricultural purposes
(crop fields, etc.) If a proposed lot or the remainder
includes an existing house, only one sewage treatment site must
be identified for the replacement and relocation of the existing
system.
|